Thursday, November 28, 2013

CNR Rao Circle underpass to be ready by January




Bruhat Bangalore Mahanagara Palike (BBMP) Commissioner M Lakshminarayana has said that the CNR Rao Circle underpass will be completed by the end of January 2014.

During the inspection of the underpass along with other BBMP officers on Monday, Lakshminarayana said the work had gained momentum after Chief Minister Siddaramaiah’s inspection in September: “The project is being jointly executed by the East Coast Constructions and Industries (ECCI) and Madhava Hytech at a total cost of Rs 30 crore. Work amounting to Rs 21 crore has already been completed.” He also said the carriageway of the underpass connecting Malleswaram and Yeshwantpur will be operational within the next 15 days. 

The Commissioner also inspected Okalipuram junction where a signal-free corridor project has been proposed. He said the State government has given its nod for the project and soil testing activity for the project had begun. “We have obtained permission from Anil Kumar Agarwal, Division Railway Manager (DRM), South Western Railways and Rs 70 crore has been deposited with the Railways,” Laxminarayana added.

Chairperson of BBMP’s standing committee for major works B Somashekar, who was present during the inspection, told Deccan Herald: “The CNR Rao underpass work started in the year 2010 and was supposed to end by December 2013 as per Chief Minister Siddaramaiah’s directions. 

However, due to factors like rains and problems with the previous contractor, the project was delayed. About 70 per cent of the work has been finished. Once the Y-shaped underpass is operational, it will ensure smoother traffic flow towards Yeshwantpur-Malleswaram and Yeshwantpur-Mekhri Circle.We are sure that the project will be completed by January.”