Here's the latest on BIAL Express way. The big news is assembly work of concrete segments has started..
This is the biggest gantry crane I have ever seen for assembly of concrete structures for any flyover. Its just huge..
It took a couple of months to assemble this huge crane..
And latest update as on today is the Railway crossing road is closed. Now all vehicles going towards Yelahanka or Doddaballapur from Hebbal need to continue straight on the highway and take the left near Coffee day/ Mahindra showroom.
And all vehicles from Yelahanka NES need to take the left at Yelahanka Police station signal and go towards old town and then take the right to reach the highway.
Today traffic was completely out of control due to sudden change of the road.