Wednesday, October 19, 2011

GET SET FOR SOME METRO ACTION

KNOW YOUR STATION 


BYAPPANAHALLI TO CRICKET STADIUM 

Viaduct: 

The piers have been completed at all the 222 locations All girder segments have been cast and segment launching of all girders has been completed from Byappanahalli to Cricket stadium.

Stations: 

All work is completed in all stations along Reach 1. 
MAGADI RD TO MYSORE ROAD TERMINAL 

Viaduct: 

1143 piles have been completed out of 1173,185 piers out of 242 and 1496 segments cast out of 2117.Launching of 112 girders has been completed 

Stations: 

99 percent of foundation works completed.Construction of concourse level pier and pier arm at Magadi Road completed.Four Platform Level Pier arm completed out of 10 and other stations. 

SWASTIK TO YESHWANTHPUR 

Viaduct: 

870 piles are completed out of 909,170 piers are cast out of 204 and segments launching of 111 spans completed.

Stations: 

50 percent of work is completed in Yeshwanthpur Soap factory and Mahalakshmi stations.53.75 percent of work is completed in Rajajinagar,Kuvempu Road and Malleshwaram stations. 

YESHWANTHPUR TO PEENYA DEPOT 

Viaduct: 

The construction work has started and piling work is in progress.878 piles have been completed out of 944 and 815 segment casting has been completed out of 1280.Launching of 45 spans completed.

Stations: 

Peenya Industrial Area Station: 194 piles completed. 

PEENYA VILLAGE STATION TO HESSARGHATTA CROSS STATION 

Viaduct: 

207 out of 450 working piles are completed at viaduct portion.

Stations: 

Jalahalli Station: All working piles completed.12 piers upto concourse level completed out of 20 

K R MARKET TO RV ROAD 

Viaduct: 

Segment casting is complete.146 piers out of 147 and 100 parapet erections complete.

Stations

: 81 percent of work is completed in KR Road,75 percent of work in Lalbagh and 58 percent in South End Circle stations,around 65 percent of work is completed in Jayanagar station,and 64 percent of work is completed in RV Road Station. 

RV ROAD TO PUTTENAHALLI CROSS 

Viaduct: 

3 test piles have been completed.468 piles have been completed out of 550 and 63 pile caps completed out of 141 and 58 piers have been completed out of 141.

Stations: 

5 test piles have been completed.409 piles have been completed out of 480.38 pile caps completed out of 72.



LOCATION: TRINITY 

ENTRY: M G ROAD (EITHER SIDES) 

EXIT:ON EITHER SIDE OF M G ROAD 

TICKET COUNTER LOCATION:AT BOTH ENTRANCES 

SERVICES NEARBY: HOTELS,BANKS AND SHOPPING AVENUES 